Application Number M/26/00050/HP
Status Application Approved

Sign up to notifications on this planning application Back to search results New search

Planning Online Status


  • Application
    Valid
    21/01/2026
  • Consultation
    End
    18/02/2026
  • Committee
    Meeting
    N/A
  • Decision

    Approval
  • Decision
    Date
    14/04/2026
  • Appeal
    Started
    N/A
  • Appeal
    Decision
    N/A
Summary
Application Number M/26/00050/HP
Location Address Ebor House Worcester Road Great Witley Worcester WR6 6JT
Proposal Proposed extension, alterations and new garage (to include removal of existing dilapidated outbuildings)
Status Approval
Application Type Householder Planning
Appeal Decision N/A

Important Dates
Application Received Date 14/01/2026
Application Valid Date 21/01/2026
Consultation Start Date 22/01/2026
Site Visited / Site Notice Date
Consultation End 18/02/2026
Advert Expiry
Committee Date (if applicable)
Committee Agenda
Decision Date 14/04/2026

Further Information
Expected Decision Level Delegated
Case Officer Matthew Webb
Parish Great Witley CP
Ward Baldwin Ward
Applicant Miss J Cowley
Agent Miss Lucy Righton, L A RIGHTON Rural Planning Consultancy
Agent Address Brickyard Cottage Hill Furze Road Bishampton Pershore WR10 2NA

Condition Details / Information Notes
The development hereby permitted shall be begun before the expiration of three years from the date of this permission. Reason: To conform with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
Unless where required or allowed by other conditions attached to this permission/consent, the development hereby approved shall be carried out in accordance with the information (including details on the proposed materials) provided on the application form and the following plans/drawings/documents – Proposed Ground Floor Plan – Dwg No. 23.34.P04 Rev B Proposed Elevations – Dwg No. 23.34.P06 Rev B Proposed Garage + Access Gates – Dwg No. 23.34.P08 Rev A Landscaping Plan – Dwg No. 23.34.P09 Rev B Site Location Plan – Dwg No. 23.34.P01 Rev A Existing + Proposed Block Plan – Dwg No. 23.34.P03 Rev C First Floor + Roof Plans – Dwg No. 23.34.P05 Rev C Reason: To define the permission in accordance with policies SWDPR01 and SWDPR03 of the South Worcestershire Development Plan Review 2026 and the National Planning Policy Framework.
The development hereby permitted shall not be occupied/first used until full details of all surface water drainage systems to serve the development have been submitted to and approved in writing by the Local Planning Authority. The approved drainage works shall be implemented in accordance with the approved details before the first occupation/use of the development hereby permitted and shall be retained thereafter. Reason: To ensure development would not result in unacceptable risk of pollution or harm to the environment and to ensure the proposed development does not exacerbate flood risk and deals with surface water run-off from the site in a sustainable manner, in accordance with policies SWDPR38, SWDPR39 and SWDPR40 of the South Worcestershire Development Plan Review 2026.
The development hereby permitted shall be carried out in strict accordance with the recommendations set out in the Preliminary Roost Assessment & Bat Survey report carried out by Sharpe Ecology dated September 2025 and submitted with this application. In particular:- - A toolbox talk will be delivered to all site workers by the licensed ecologist, prior to the commencement of any works impacting the building. - Immediately prior to the start of demolition/key destructive works, a detailed internal and external visual inspection (using torches and endoscopes where necessary) will be carried out by a licensed ecologist. Any bats encountered will be caught by hand and removed to a bat box which will be located a suitable tree within the site (as identified by onsite ecologist). The bat box (e.g. Schwegler 2FN, Large WoodStone MultiChamber Bat Box, Kent Bat Box or similar) will be put up prior to the commencement of key destructive works and will be located as high as possible on the southwest, south or southeast side of the tree, with a clear flight path for bat entering and exiting the box. The works will then proceed immediately in strict adherence to the Bat Mitigation Licence conditions and the precautionary working methods described here. - The removal of roof tiles and other roof structures plus any other potential roost features identified by the on-site ecologist must be carried out by hand and under strict supervision of the licensed ecologist. Although there are no timing constraints to works, key destructive works that could impact bats will be timed to avoid cold or adverse weather conditions, following best practice guidance. - Compensation for the loss of the brown long-eared bat feeding perch would be the provision of 1x cavity bat box (located on suitable tree within the site). Suitable cavity bat boxes include Schwegler 2FN, Greenwood’s Small Hollow Bat Box or Vivara Pro WoodStone Bat Box. - The loss of three soprano pipistrelle day roosts, two common pipistrelle day roosts, one whiskered bat day roost and one brown long-eared bat day roost will be compensated for through the inclusion of 4x integrated bat boxes on the new extension and detached garage, and the inclusion of 3x modified ridge tiles on the new extension and detached garage. Suitable integrated bat boxes include Build-in WoodStone Bat Box, 1FR Schwegler Bat Tube, Ibstock Enclosed Bat Box ‘B’, or Bat Access Brick (allows access to wall cavity, and a cavity chamber may need to be constructed to maintain an area free of insulating material where bats can roost, and with bitumastic felt lining the rear internal wall). - The lighting scheme shall: minimise lighting levels across the site; reduce upward light spill through directional lighting angled no greater than 70° and low-level dark-sky lighting (e.g. low-level bollard LED); limit illumination during sensitive periods by avoiding lighting immediately after dusk and before dawn; use sensor-activated lighting so that it operates only when required; and utilise narrow-spectrum, low-impact light sources with no UV content (such as low-pressure sodium, warm white LED, or red-spectrum lighting over 600nm, RA 60), while avoiding broad-spectrum or high-UV sources including white LED, high-pressure sodium, metal halide and mercury lighting. - The vegetation (trees, scrub, ivy cover, hedgerows etc.) and the timber barn all provided suitable opportunities for nesting birds. Therefore, in order to avoid the risk of harm/disturbance to nesting birds, any vegetation cutting back/removal and key destructive works to the timber barn should be undertaken outside of the peak bird nesting season (March to August inclusive) to avoid potential conflict with the legislation concerning breeding birds. If vegetation removal/demolition works cannot be scheduled to avoid the bird nesting season, then a check by an ecologist immediately prior to commencement of clearance works will be required, and if nests are found to be present, they should be adequately protected until breeding has finished and the nest is no longer in use. - The precise locations of all stands of Japanese knotweed should be identified, and the stands of Japanese knotweed should be treated and eradicated. - As an enhancement 5x additional modified ridge tiles within new extension and garage, and the inclusion of 3x integrated swift nest boxes and 2x house sparrow terrace nest boxes within new extension and garage. Reason: To ensure the development contributes to the conservation and enhancement of biodiversity within the site and the wider area in accordance with policy SWDPR29 of the South Worcestershire Development Plan Review 2026.
Prior to their installation, details of the materials to be used in the construction of the external surfaces listed below hereby permitted have been submitted to and approved in writing by the local planning authority. The details to be submitted shall include:- Front (historic/original) section of the building - A full repair schedule for all works proposed to the front section, including methodology and materials for any repairs, refurbishment, or replacement. - 1:10 scale drawings of all new or replacement windows and doors to the front section, including: position within the reveal/opening, cross sections showing transoms, mullions, glazing bars, sash boxes (where applicable), and details of materials, finish, and glazing. - Samples of all new external and internal materials to be used in the front section, including (but not limited to) brickwork, mortars, timber, joinery finishes, roofing materials, and any other visible components. External material details of all new works to the extensions, garage and drive surface, including: - specification, type, colour, texture, size, coursing and finish of brickwork; - type, colour, texture, size and design of roof coverings; - design, materials, colour and finish of all new external windows and doors. - type and finish of the proposed driveway surfacing materials. The development shall be carried out using the materials as approved. Reason: To ensure that the new materials are in keeping with the surroundings and/or represent quality design in accordance with policy SWDPR05, SWDPR09, SWDPR28 and SWDPR 33 of the South Worcestershire Development Plan Review.
(A) No development shall take place until a programme of archaeological work, including a Written Scheme of Investigation, has been submitted to and approved by the local planning authority in writing. The scheme shall include an assessment of significance and research questions; and: 1) The programme and methodology of site investigation and recording. 2) The programme for post investigation assessment. 3) Provision to be made for analysis of the site investigation and recording. 4) Provision to be made for publication and dissemination of the analysis and records of the site investigation. 5) Provision to be made for archive deposition of the analysis and records of the site investigation. 6) Nomination of a competent person or persons/organisation to undertake the works set out within the Written Scheme of Investigation. (B) The development shall not be commenced until the site investigation has been completed in accordance with Part A of the condition. The development shall not be occupied until the post investigation assessment has been completed in accordance with the programme set out in the Written Scheme of Investigation approved under Part A and the provision made for analysis, publication and dissemination of results and archive deposition has been secured. Reason: In accordance with the requirements of paragraphs 207 and 218 of the National Planning Policy Framework (as amended) and SWDPR 09 & 33 of the South Worcestershire Development Plan Review.
The materials to be used in the construction of the external framing and surfaces of the PV panels hereby permitted shall be in accordance with the submitted solar panels datasheet Marley SolarTile. Reason: To protect, conserve and enhance the significance of heritage assets and to ensure that the new materials are in keeping with the surroundings and represent quality design in accordance with Policies SWDPR05, SWDPR09, SWDPR28, and SWDPR33 of the South Worcestershire Development Plan Review.
Prior to the first occupation of the development hereby permitted, details of renewable and/or low carbon energy generation measures shall be submitted to and approved in writing by the Local Planning Authority. The measures shall contribute to at least 20% of the predicted energy requirements of the development. The details to be submitted shall include:- - the overall predicted energy requirements of the approved development; - the predicted energy generation from the proposed renewable/low carbon energy measures; and - an implementation timetable for the proposed measures. The development shall be carried out in accordance with the approved details. Reason - To ensure the development supports the delivery of low carbon/renewable energy and safeguards natural resources in accordance with policy SWDPR37 of the South Worcestershire Development Plan Review 2026.
Positive and Proactive Statement. In dealing with this application, the Council has worked with the applicant in the following ways: - seeking further information following receipt of the application; - seeking amendments to the proposed development following receipt of the application; In such ways the Council has demonstrated a positive and proactive manner in seeking solutions to problems arising in relation to the planning application.

Copyright Notice

Plans, drawings and material submitted to the council are protected by the copyright acts (section 47, 1988 act). You may only use material which is downloaded and/or printed for consultation purposes, to compare current applications with previous schemes and to check whether developments have been completed in accordance with approved plans. Further copies must not be made without the prior permission of the copyright owner.

Tick here to show you have read and agree with the Copyright Notice.

Document Download Tips

  • In order to view the documents please ensure you have ticked the Copyright Notice box above.
  • In order to view PDF documents, you will need to have the free Adobe Acrobat Reader software installed on your computer. Click here to download.
  • To view individual documents click on the 'Document Type' on the row you require and the document will open as an Adobe Acrobat pdf.
  • To download multiple documents in one go, tick all the boxes relating to the documents you wish to view and click Download selected files button.
  • If you wish to download ALL documents place a tick in the box in the header row and click 'Download Selected Files' button.
  • Note: some devices such as iPads that use iOS browsers do not have the standard capability to download multiple files as a default function. If you are experiencing difficulties you may need to download a free application to enable you to do this - known as a zip file. Go to the AppStore to download a zip file ‘app’.

How to reorder or group rows

Click on a column heading for the ability to sort the ‘group’ listing in ascending or descending order by using the up/down arrows. This is useful to sort by ‘name/organisation’.

Document Type Date Description File Size Drawing/Rev Number
Application Documents
Application Plans
Statutory Consultee Response
Decision

Consultation Responses

Neighbour List


In addition to consultations with the consultee listed, we will publicise the application in accordance with national requirements and our local policy. This publicity usually takes the form of letters to nearby properties, the posting of site notices and/or the placing of a public notice in our local newspapers.


Address Sent Reply Received
Perhill Plants Nursery Worcester Road Great Witley WORCESTER WR6 6JT 22/01/2026

Consultee List


Name Organisation Sent Reply Due Reply Received
Aidan Smyth MHDC Archaeology & Planning Advisor 22/01/2026 12/02/2026 23/01/2026
Cllr Pam Cumming Baldwin Ward 22/01/2026 12/02/2026 22/01/2026
Cllr Paul Cumming Baldwin Ward 22/01/2026 12/02/2026 01/02/2026
Drainage Engineer Engineers - S.W. Land Drainage Partnership 22/01/2026 12/02/2026 30/01/2026
Highways County Highways 22/01/2026 12/02/2026 23/01/2026
MHDC Heritage Officer MHDC Heritage Officer 22/01/2026 12/02/2026
MHDC Tree and Landscape Officer MHDC Tree and Landscape Officer 22/01/2026 12/02/2026 25/02/2026
Midlands Business Team Historic England 22/01/2026 12/02/2026 06/02/2026
Mrs Elaine Artherton Hereford & Worcester Gardens Trust 22/01/2026 12/02/2026 01/02/2026
Rachel Lambert Great Witley Parish Council 22/01/2026 12/02/2026 11/02/2026
The Gardens Trust - Consult The Gardens Trust 22/01/2026 12/02/2026

Constraints List


Constraints List
Paper: Berrows Journal - Thursday
CIL009 - Non-Urban Area
Area of Special Control of Advertisements
Surface Water: 1 in 1000 extent
Park or Garden : Grade II*. H.E Ref: 1000901. Park & Garden (AT RISK). Witley Court. PG/1000901
Park or Garden Grade I or II* Only: Grade II*. H.E Ref: 1000901. Park & Garden (AT RISK). Witley Court. PG/1000901
Outside SWDP Development Boundary
Water Supply. If Major Application consultation required with Water Supply Company
Policy Case HLA - MIG/16/00822/HOU. Perhill Plants Nursery, Worcester Road, Great Witley, Worcester, WR6 6JT. Change of use of existing building to a live/work unit, including new entrance door to front facade and minor alterations.. Open Market. Small windfall (HLA only)
SWDP 15: Designated Rural Areas
SWDP 5: Protect and Enhance
SWDP 6: Historic Park and Garden
Hundred Pool within 500m
No associated appeals