| Condition Details / Information Notes |
| The development hereby permitted shall be begun before the expiration of three years from the date of this permission.
Reason: To conform with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| Unless where required or allowed by other conditions attached to this permission/consent, the development hereby approved shall be carried out in accordance with the information (including details on the proposed materials) provided on the application form and the following plans/drawings/documents –
Location Plan Existing & Proposed Site Plans drawing No 1 revision A
Existing Ground Floor Plan and Elevations drawing No 2
Proposed Extension Ground Floor Plan and Elevations drawing No 3 revision A
Reason: To define the permission. |
| Prior to the first use/occupation of the development hereby permitted, the details set out in the submitted Water Management Statement shall be fully implemented and remain thereafter.
Reason: To ensure that an appropriate sustainable drainage system is provided to serve the development in accordance with policy SWDP29 of the South Worcestershire Development Plan 2016. |
| The development hereby permitted shall be carried out in strict accordance with the recommendations set out in the Preliminary Bat Roost Appraisal, carried by Breakwell Ecology dated 6 May 2025 and submitted with this application. In particular:
- Works that involve disturbance of the main roof are carried out under soft demolition protocol, whereby soffits, eaves, and roof tiles are removed
by hand and inspected carefully before being discarded. If any bats are found, works are to stop immediately, and a bat-licensed ecologist contacted for advice on how to proceed.
- Prior to the first use / occupation of the development hereby approved, 1no. bird nesting box (e.g. a house sparrow terrace) shall be installed under the eaves of the north or east facing elevation of the dwelling and shall remain thereafter.
- Prior to the first use / occupation of the development hereby approved, 1no. bat box shall be installed within the land ownership of the site (e.g. Ibstock enclosed bat box, Habibat bat box, Schwegler Wall-mounted Bat Shelter 2FE, Schwegler 2F Bat Box). The box should be installed at least 4m above ground-level, facing south (or southwest/southeast), and not placed above windows and shall remain thereafter
Reason: To ensure the development contributes to the conservation and enhancement of biodiversity within the site and the wider area in accordance with policy SWDP22 of the South Worcestershire Development Plan. |
| Positive and Proactive Statement. No problems have arisen in dealing with this application. The planning application sought an acceptable form of development consistent with the requirements of relevant policies and material considerations. No amendments or alterations were therefore required and no further positive or proactive action was deemed necessary. |
| Buildings, and particularly roofs and the spaces underneath them, are frequently used as roosting sites by bats. Bats and their 'roost' sites are protected under the Wildlife and Countryside Act 1981 (as amended) and the Conservation of Habitats & Species Regulations 2017 (as amended), the latter of which deems them a European Protected Species. It is a criminal offence to damage or destroy a roost (even if bats are not occupying the roost at the time), to deliberately kill or injure a bat, disturb a bat in its roost, or intentionally or recklessly obstruct access to a bat roost. Planning consent for a development does not provide a defence against prosecution under these acts.
Any removal of roof and wall coverings including roof tiles, slates, hanging tiles, timber boarding, soffit boxes and facia boards shall be carried out carefully by hand. If bats or any sign of bats such as an accumulation of droppings are encountered at any stage of work, work must cease immediately and advice sought from an appropriately licenced bat ecologist on how to proceed lawfully. All contractors working on site should be made aware of the advice and provided with the contact details of a relevant ecological consultant.
|
| The applicant must be aware of their obligations towards the public right of way as follows: No disturbance of, or change to, the surface of the path or part thereof should be carried out without written consent (this includes laying concrete, tarmac or similar)
No diminution in the width of the right of way available for use by the public.
Building materials must not be stored on the right of way.
Vehicle movements and parking to be arranged so as not to unreasonably interfere with the public's use of the right of way.
No additional barriers are placed across the right of way. No stile, gate, fence or other structure should be created on, or across, a public right of way without written consent of the Highway Authority.
The safety of the public using the right of way is to be ensured at all times. |