| Condition Details / Information Notes |
| The development hereby permitted shall be begun before the expiration of three years from the date of this permission.
Reason: To conform with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| Unless where required or allowed by other conditions attached to this permission/consent, the development hereby approved shall be carried out in accordance with the information (including details on the proposed materials) provided on the application form and the following plans-
2023/83/11 Rev. D
2023/83/15
Reason: To define the permission. |
| Demolition, clearance or construction work and deliveries to and from the site in connection with the development hereby approved shall only take place between the hours of 08.00 and 18.00hrs Monday to Friday and 08.00 and 13.00hrs on a Saturday. There shall be no demolition, clearance or construction work or deliveries to and from the site on Sundays or Bank Holidays.
Reason - To preserve the amenities of the locality in accord with Policy SWDP21 of the South Worcestershire Development Plan. |
| The development hereby permitted shall not be occupied/first used until full details of all surface water drainage systems to serve the evelopment have been submitted to and approved in writing by the Local Planning Authority. The approved drainage works shall be implemented in accordance with the approved details before the first occupation/use of the development hereby permitted and shall be retained thereafter.
Reason: To ensure development does not exacerbate flood risk and deals with surface water run-off from the site in a sustainable manner, in accordance with policies SWDP28, SWDP29 and SWDP 30 of the South Worcestershire Development Plan. |
| Prior to first occupation of the dwelling herby approved, details to demonstrate that the predicted non recycled water consumption of the property will be no more than 110 litres per day per person shall be submitted in writing to the Local Planning Authority for approval.
Reason: To mitigate the impacts of climate change in accordance with policy SWDP30 of the South Worcestershire Development Plan.
|
| Unless otherwise agreed by the Local Planning Authority development, other than that required to be carried out as part of an approved scheme of remediation, must not commence until conditions 1 to 6 have been complied with:
1. A preliminary risk assessment must be carried out. This study shall take the form of a Phase I desk study and site walkover and shall include the identification of previous site uses, potential contaminants that might reasonably be expected given those uses and any other relevant information. The preliminary risk assessment report shall contain a diagrammatical representation (conceptual model) based on the information above and shall include all potential contaminants, sources and receptors to determine whether a site investigation is required and this should be detailed in a report supplied to the Local Planning Authority. The risk assessment must be approved in writing before any development takes place.
2. 2. Where an unacceptable risk is identified a scheme for detailed site investigation must be submitted to and approved in writing by the Local Planning Authority prior to being undertaken. The scheme must be designed to assess the nature and extent of any contamination and must be led by the findings of the preliminary risk assessment. The investigation and risk assessment scheme must be compiled by competent persons and must be designed in accordance with the Environment Agency's "Land Contamination: Risk Management" guidance.
3. Detailed site investigation and risk assessment must be undertaken and a written report of the findings produced. This report must be approved by the Local Planning Authority prior to any development taking place. The investigation and risk assessment must be undertaken by competent persons and must be conducted in accordance with the Environment Agency's "Land Contamination: Risk Management" guidance.
4. Where identified as necessary a detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to identified receptors must be prepared and is subject to the approval of the Local Planning Authority in advance of undertaking. The remediation scheme must ensure that the site will not qualify as Contaminated Land under Part 2A Environmental Protection Act 1990 in relation to the intended use of the land after remediation.
5. The approved remediation scheme must be carried out in accordance with its terms prior to the commencement of development, other than that required to carry out remediation, unless otherwise agreed in writing by the Local Planning Authority.
6. Following the completion of the measures identified in the approved remediation scheme a validation report that demonstrates the effectiveness of the remediation carried out must be produced, and is subject to the approval of the Local Planning Authority prior to the occupation of any buildings.
7. In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported in writing immediately to the Local Planning Authority. An investigation and risk assessment must be undertaken and where necessary a remediation scheme must be prepared, these will be subject to the approval of the Local Planning Authority. Following the completion of any measures identified in the approved remediation scheme a validation report must be prepared, which is subject to the approval in writing of the Local Planning Authority prior to the occupation of any buildings.
Reason: To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors.
|
| The Development hereby approved shall not be occupied until an area has been laid out within the curtilage of each dwelling for the parking of two cars per dwelling. This area shall thereafter be retained for the purpose of parking a vehicle only.
REASON: In the interests of highway safety and to ensure the free flow of traffic using the adjoining highway.
|
| Prior to the development hereby approved being first occupied, the existing workshops as shown on the approved plans shall be demolished and the site cleared of all the resulting materials (apart from materials used in the construction of the development hereby approved).
Reason: In the interests of visual amenity in accordance with policies SWDP21 and SWDP25 of the South Worcestershire Development Plan. |
| Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (as amended) (or any order revoking, re-enacting, substituting, amending, extending, consolidating, replacing or modifying that Order), no new boundary treatment other than that expressly authorised by this permission shall be carried out on the application site following the completion of the development hereby permitted.
Reason: To ensure the development is implemented in accordance with the permission. |
| Positive and Proactive Statement. No problems have arisen in dealing with this application. The planning application sought an acceptable form of development consistent with the requirements of relevant policies and material considerations. No significant amendments or alterations were therefore required and no further positive or proactive action was deemed necessary. |