| Application Number | M/24/01635/GPDQ |
| Status | Application Approved |
| Application Valid |
|---|
| 11/12/2024 |
| Consultation End |
|---|
| 06/02/2025 |
| Committee Meeting |
|---|
| N/A |
| Decision |
|---|
| Approval |
| Decision Date |
|---|
| 13/02/2025 |
| Appeal Started |
|---|
| N/A |
| Appeal Decision |
|---|
| N/A |
| Summary | |
| Application Number | M/24/01635/GPDQ |
| Location Address | New Barn Farm Gadfield Elm Staunton Gloucester GL19 3PE |
| Proposal | Notification for Prior Approval for the proposed change of use of an agricultural barn to 10no. dwellinghouses (Class C3), and associated operational development |
| Status | Approval |
| Application Type | GPDQ - agricultural to C3 dwellinghouse |
| Appeal Decision | N/A |
| Important Dates | |
| Application Received Date | 21/11/2024 |
| Application Valid Date | 11/12/2024 |
| Consultation Start Date | 12/12/2024 |
| Site Visited / Site Notice Date | |
| Consultation End | 06/02/2025 |
| Advert Expiry | |
| Committee Date (if applicable) | |
| Committee Agenda | |
| Decision Date | 13/02/2025 |
| Further Information | |
| Expected Decision Level | Delegated |
| Case Officer | Laura Saich |
| Parish | Eldersfield CP |
| Ward | Longdon Ward |
| Applicant | Mr William Larkins |
| Agent | Mr Stuart Dudley, SJD Architects & Developments Ltd |
| Agent Address | The Estate Office Off Grimley Lane Finstall Bromsgrove B60 3AF |
| Condition Details / Information Notes |
| Unless where required or allowed by other conditions attached to this permission/consent, the development hereby approved shall be carried out in accordance with the information (including details on the proposed materials) provided on the application form and the following plans/drawings/documents – SJD-335-001 Location and Existing & Proposed Block Plan SJD-335-007 Proposed Barn 1 Floor Plan and Elevations SJD-335-008 Proposed Barn 4 Floor Plan and Elevations SJD-335-009 Proposed Site Sections SJD-335-011 Existing and Proposed Barn 1 and Barn 4 Sections Reason: To define the permission. |
| The development hereby permitted shall be carried out in strict accordance with the recommendations set out in the bat survey report carried out by Dr Stefan Bodnar dated 14th October 2024 and submitted with this application. Reason: To ensure the development contributes to the conservation and enhancement of biodiversity within the site and the wider area in accordance with policy SWDP22 of the South Worcestershire Development Plan. |
| Buildings, and particularly roofs and the spaces underneath them, are frequently used as roosting sites by bats. Bats and their 'roost' sites are protected under the Wildlife and Countryside Act 1981 (as amended) and the Conservation of Habitats & Species Regulations 2010, the latter of which deems them a European Protected Species. It is a criminal offence to deliberately kill or injure a bat, to disturb or destroy a bat roost or to obstruct an entrance to a roost. If evidence of bats is found, work should stop immediately and an ecological consultant contacted for advice on the best way to proceed. All contractors working on site should be made aware of the advice and provided with the contact details of a relevant ecological consultant. |
| In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported immediately to the Local Planning Authority. The applicant is advised to immediately seek the advice of an independent geo-environmental consultant experienced in contaminated land risk assessment, including intrusive investigations and remediation. No further works should be undertaken in the areas of suspected contamination, other than that work required to be carried out as part of an approved remediation scheme, unless otherwise agreed by the Local Planning Authority, until requirements 1 to 4 below have been complied with: 1. Detailed site investigation and risk assessment must be undertaken by competent persons in accordance with the Environment Agency's 'Land Contamination: Risk Management' guidance and a written report of the findings produced. The risk assessment must be designed to assess the nature and extent of suspected contamination and approved by the Local Planning Authority prior to any further development taking place. 2. Where identified as necessary, a detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to identified receptors must be prepared and is subject to the approval of the Local Planning Authority in advance of undertaking. The remediation scheme must ensure that the site will not qualify as Contaminated Land under Part 2A Environmental Protection Act 1990 in relation to the intended use of the land after remediation. 3. The approved remediation scheme must be carried out in accordance with its terms prior to the re-commencement of any site works in the areas of suspected contamination, other than that work required to carry out remediation, unless otherwise agreed in writing by the Local Planning Authority. 4. Following completion of measures identified in the approved remediation scheme a verification report that demonstrates the effectiveness of the remediation carried out must be produced and is subject to the approval of the Local Planning Authority prior to the occupation of any buildings on site. Reason: To ensure that the risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property, and ecosystems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors. |
| Application information indicates asbestos containing material (ACM) (cement sheeting and high wall cladding) is present within the buildings. Consideration should be given to the presence of ACMs and material removed during alterations should be disposed of appropriately such that the development site may not be considered contaminated land under Part 2A of the Environmental Protection Act 1990 at a later date. Appropriate asbestos surveys prior to demolition/alterations and handling of ACMs during works should be undertaken by competent and qualified professionals with experience of surveying and handling ACMs. |
| Positive and Proactive Statement. No problems have arisen in dealing with this application. The planning application sought an acceptable form of development consistent with the requirements of relevant policies and material considerations. No amendments or alterations were therefore required and no further positive or proactive action was deemed necessary. |
Plans, drawings and material submitted to the council are protected by the copyright acts (section 47, 1988 act). You may only use material which is downloaded and/or printed for consultation purposes, to compare current applications with previous schemes and to check whether developments have been completed in accordance with approved plans. Further copies must not be made without the prior permission of the copyright owner.
Tick here to show you have read and agree with the Copyright Notice.
Document Download Tips
How to reorder or group rows
Click on a column heading for the ability to sort the ‘group’ listing in ascending or descending order by using the up/down arrows. This is useful to sort by ‘name/organisation’.
In addition to consultations with the consultee listed, we will publicise the application in accordance with national requirements and our local policy. This publicity usually takes the form of letters to nearby properties, the posting of site notices and/or the placing of a public notice in our local newspapers.
| Address | Sent | Reply Received |
|---|---|---|
| Dobbshill Farm Staunton GLOUCESTER GL19 3PD | 12/12/2024 |
| Name | Organisation | Sent | Reply Due | Reply Received |
|---|---|---|---|---|
| Cllr Jennie Watkins | Longdon Ward | 12/12/2024 | 02/01/2025 | |
| Highways | County Highways | 12/12/2024 | 02/01/2025 | |
| MHDC Natural Heritage & Biodiversity Officer | MHDC Natural Heritage & Biodiversity | 12/12/2024 | 02/01/2025 | |
| Worcestershire Regulatory Services (Enquiries) | Worcestershire Regulatory Services | 12/12/2024 | 02/01/2025 |
| Constraints List |
| CIL009 - Non-Urban Area |
| Paper: Malvern Gazette - Friday |
| Outside SWDP Development Boundary |
| Public Right of Way: Type- Footpath. Path No- EF-638 C |
| Surface Water: 1 in 1000 extent |
| Water Supply. If Major Application consultation required with Severn Trent (Welsh Water if in Bockleton Parish) |
| SWDP 15: Designated Rural Areas |
| SWDP 5: Protect and Enhance |
| Local Wildlife Site within 100m: Gadbury Bank Fort |
| No associated appeals |