| Application Number | M/24/01208/FUL |
| Status | Application Approved |
| Application Valid |
|---|
| 16/09/2024 |
| Consultation End |
|---|
| 07/10/2024 |
| Committee Meeting |
|---|
| N/A |
| Decision |
|---|
| Approval |
| Decision Date |
|---|
| 09/10/2024 |
| Appeal Started |
|---|
| N/A |
| Appeal Decision |
|---|
| N/A |
| Summary | |
| Application Number | M/24/01208/FUL |
| Location Address | Units 26 And 27 Link Business Centre Link Way Malvern WR14 1UQ |
| Proposal | Proposed extension to industrial unit to provide a new vehicle workshop |
| Status | Approval |
| Application Type | Full planning permission |
| Appeal Decision | N/A |
| Important Dates | |
| Application Received Date | 29/08/2024 |
| Application Valid Date | 16/09/2024 |
| Consultation Start Date | 16/09/2024 |
| Site Visited / Site Notice Date | |
| Consultation End | 07/10/2024 |
| Advert Expiry | |
| Committee Date (if applicable) | |
| Committee Agenda | |
| Decision Date | 09/10/2024 |
| Further Information | |
| Expected Decision Level | Delegated |
| Case Officer | Laura Saich |
| Parish | Malvern CP |
| Ward | Link Ward |
| Applicant | Mr Jeffery, RPM Motors Limited |
| Agent | Mr Jon Hughes, Jon Hughes Architectural Services |
| Agent Address | Well Park Barn Edmonton Wadebridge PL27 7JA |
| Condition Details / Information Notes |
| The development hereby permitted shall be begun before the expiration of three years from the date of this permission. Reason: To conform with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| Unless where required or allowed by other conditions attached to this permission/consent, the development hereby approved shall be carried out in accordance with the information (including details on the proposed materials) provided on the application form and the following plans/drawings/documents – [insert all approved plan numbers]. Reason: To define the permission. |
| Prior to the first use/occupation of the development hereby permitted, the details set out in the submitted Water Management Statement shall be fully implemented and remain thereafter. Reason: To ensure that an appropriate sustainable drainage system is provided to serve the development in accordance with policy SWDP29 of the South Worcestershire Development Plan 2016. |
| In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported immediately to the Local Planning Authority. The applicant is advised to immediately seek the advice of an independent geo-environmental consultant experienced in contaminated land risk assessment, including intrusive investigations and remediation. No further works should be undertaken in the areas of suspected contamination, other than that work required to be carried out as part of an approved remediation scheme, unless otherwise agreed by the Local Planning Authority, until requirements 1 to 4 below have been complied with: 1. Detailed site investigation and risk assessment must be undertaken by competent persons in accordance with the Environment Agency’s ‘Land Contamination: Risk Management’ guidance and a written report of the findings produced. The risk assessment must be designed to assess the nature and extent of suspected contamination and approved by the Local Planning Authority prior to any further development taking place. 2. Where identified as necessary, a detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to identified receptors must be prepared and is subject to the approval of the Local Planning Authority in advance of undertaking. The remediation scheme must ensure that the site will not qualify as Contaminated Land under Part 2A Environmental Protection Act 1990 in relation to the intended use of the land after remediation. 3. The approved remediation scheme must be carried out in accordance with its terms prior to the re-commencement of any site works in the areas of suspected contamination, other than that work required to carry out remediation, unless otherwise agreed in writing by the Local Planning Authority. 4. Following completion of measures identified in the approved remediation scheme a verification report that demonstrates the effectiveness of the remediation carried out must be produced and is subject to the approval of the Local Planning Authority prior to the occupation of any buildings on site. Reason: To ensure that the risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property, and ecosystems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors. |
| Cadent Gas Ltd own and operate the gas infrastructure within the area of your development. There may be a legal interest (easements and other rights) in the land that restrict activity in proximity to Cadent assets in private land. The applicant must ensure that the proposed works do not infringe on legal rights of access and or restrictive covenants that exist. If buildings or structures are proposed directly above the apparatus the development may only take place following diversion of the apparatus. The applicant should apply online to have apparatus diverted in advance of any works, by visiting cadentgas.com/diversions Prior to carrying out works, including the construction of access points, please register on www.linesearchbeforeudig.co.uk to submit details of the planned works for review, ensuring requirements are adhered to. |
| Positive and Proactive Statement. No problems have arisen in dealing with this application. The planning application sought an acceptable form of development consistent with the requirements of relevant policies and material considerations. No amendments or alterations were therefore required and no further positive or proactive action was deemed necessary. |
Plans, drawings and material submitted to the council are protected by the copyright acts (section 47, 1988 act). You may only use material which is downloaded and/or printed for consultation purposes, to compare current applications with previous schemes and to check whether developments have been completed in accordance with approved plans. Further copies must not be made without the prior permission of the copyright owner.
Tick here to show you have read and agree with the Copyright Notice.
Document Download Tips
How to reorder or group rows
Click on a column heading for the ability to sort the ‘group’ listing in ascending or descending order by using the up/down arrows. This is useful to sort by ‘name/organisation’.
In addition to consultations with the consultee listed, we will publicise the application in accordance with national requirements and our local policy. This publicity usually takes the form of letters to nearby properties, the posting of site notices and/or the placing of a public notice in our local newspapers.
| Address | Sent | Reply Received |
|---|---|---|
| G Webb Automation Howsell Road MALVERN WR14 1TF | 16/09/2024 | |
| Garage Rear Of Express Buildings 2A Howsell Road MALVERN WR14 1TF | 16/09/2024 | |
| Unit 11 Link Business Centre Link Way MALVERN WR14 1UQ | 16/09/2024 | |
| Unit 12 Link Business Centre Link Way MALVERN WR14 1UQ | 16/09/2024 | |
| Unit 25 Link Business Centre Link Way MALVERN WR14 1UQ | 16/09/2024 | |
| Unit 5 Howsell Road Industrial Estate MALVERN WR14 1UJ | 16/09/2024 | |
| Unit 6 Howsell Road Industrial Estate MALVERN WR14 1UJ | 16/09/2024 | |
| Unit 6A Howsell Road Industrial Estate MALVERN WR14 1UJ | 16/09/2024 | |
| Unit 6B Howsell Road Industrial Estate MALVERN WR14 1UJ | 16/09/2024 | |
| Unit 8 Link Business Centre Link Way MALVERN WR14 1UQ | 16/09/2024 | |
| Units 5A And 5B Howsell Road Industrial Estate MALVERN WR14 1UJ | 16/09/2024 | |
| Units 9 And 10 Link Business Centre Link Way MALVERN WR14 1UQ | 16/09/2024 |
| Name | Organisation | Sent | Reply Due | Reply Received |
|---|---|---|---|---|
| Defence Estates Safeguarding | 16/09/2024 | 07/10/2024 | ||
| Cllr Fran Victory | Link Ward | 16/09/2024 | 07/10/2024 | |
| Cllr Neville Mills | Link Ward | 16/09/2024 | 07/10/2024 | |
| Councillor K.H. Chan | Link Ward | 16/09/2024 | 07/10/2024 | |
| Drainage Engineer | Engineers - S.W. Land Drainage Partnership | 16/09/2024 | 07/10/2024 | |
| Highways | County Highways | 16/09/2024 | 07/10/2024 | |
| MHDC Economic Development | MHDC Economic Development | 16/09/2024 | 07/10/2024 | |
| Network Rail | Network Rail Infrastructure Ltd | 16/09/2024 | 07/10/2024 | |
| Town Council Clerk | Malvern Town Council | 16/09/2024 | 07/10/2024 | |
| Worcester Regulatory Services Contaminated Land | Worcestershire Regulatory Services | 16/09/2024 | 07/10/2024 | |
| Worcestershire Regulatory Services - Nuisance | Worcestershire Regulatory Services | 16/09/2024 | 07/10/2024 |
| Constraints List |
| Policy Case HLA - MIG/04/00659/HOU. Ground Floor, 2A Express Buildings, Howsell Road. Conversion of ground floor office accommodation to 2 flats.. Open Market. Small windfall (HLA only) |
| Policy Case ELA - 09/01685. Link Business Centre, Link Way, Malvern. Construction of 7 no. single storey industrial units with mezzanine floors for storage. Complete. |
| SWDP 2: Development Boundary |
| Neighbourhood Plan: NPA Boundaries |
| SWDP 5: Urban - Unsurveyed |
| Neighbourhood Plan: Existing Employment Sites |
| Paper: Malvern Gazette - Friday |
| CIL003 - Main Urban Area |
| Surface Water: 1 in 30 extent. |
| Surface Water: 1 in 100 extent. |
| Surface Water: 1 in 1000 extent |
| Interferometer Area. INFER/7018 - |
| Water Supply. If Major Application consultation required with Severn Trent (Welsh Water if in Bockleton Parish) |
| Contaminated Land |
| Policy Case ELA - 08/01085. 2A Howsell Road, Malvern, Worcestershire, WR14 1TF. Change of use from B1 to B2 to allow MOT Testing within current business premises.. Complete. |
| No associated appeals |